Do I need a contract with a builder?
It’s a really good idea to have a contract for your build project. We will ask you to sign a contract to progress with drawings and it’s a good idea to have a contract to progress with a builder. They are there to protect both sides in case something goes wrong. Common things to go ‘wrong’ include certain works a client thought was included and the building didn’t, the builder claiming additional time or money for things that are ‘extra’ and a builder going to another job leaving work unfinished for a long time.
There are industry standard contracts you could use (they are contracts you will need to pay for) or you could use a bespoke contract written by yourself or your builder.
The RIBA domestic building contract is available here:
https://www.architecture.com/digital-practice-tools/riba-contracts/riba-domestic-building-contract
The JCT Building Contract for a Home Occupier is available here:
https://www.jctltd.co.uk/product/building-contract-for-a-home-owner-occupier
If you use a bespoke contract, at the very least it should include:
– Your name and the name of the builder (or company name)
– Start and completion date and what counts as completed.
– The price including VAT. Some large ticket items such as windows may have a provisional sum against them if they rely on other companies to quote.
– What you’re expecting of the project for the price and how is this defined? It could be the drawings, it could be a very detailed description.
– Procedure to agree extra works – what’s the cost, how does this impact timescales.
– Payment terms – how and when will payments be due. This could be every four weeks (or two on a small project,) or it could be at milestones such as foundations, walls, roof etc. If the project is over £100,000 in value, there are fairer ways to attribute payments by using valuations.
‘Standard’ industry contracts don’t allow for advances payments / deposits because they create unnecessary risk. We don’t ask for up front payments and would recommend avoiding paying others upfront. If you really must because of a materials issue, it may be worth asking to pay a materials invoice directly so the materials belong to you.
If you really really really need to pay cash, get a signed receipt as you hand it over, not a promise for a receipt later.
Include a retention. It’s usually 5% of the entire contract value until the project is complete when you pay a further 2.5%. The remaining 2.5% is retained for a period agreed (3, 6 or 12months depending on size of project) to allow for any defects. Retentions are being looked into by the Government due to the number of insolvencies, so policies may change at some point. JCT may also be looking at making changes to the contracts in 2024, so do check if you use a JCT contract.
– Working hours – noisy works are restricted to 8-6 Monday to Friday, 8-1 on a Saturday but you may wish to restrict access further say for weekends. However there may be an advantage to allowing access if it helps keep the timescales on track.
– Insurances and guarantees – your builder needs public liability and building cover
– Dispute resolution – whilst it’s better to try to resolve an issue between yourselves (it’s fastest and cheapest,) sometimes a third party will be needed to help resolve issues. They are less formal than court proceedings and faster. Court is a sloooooooooow process. The RIBA and CIOB both have resolution services, they are paid services – as is court.
– What happens if the works take longer than expected?
– Access and on site facilities for the builders – water, electricity, toilets, material storage etc.
If your builder does not want to sign a contract, then walk away and expect them to do the same if you do not want to sign one.